2.30 (TD1) Phase II Development (p17): How many v1 prototype devices are required per each customer (5 organisations)? How long do you expect the testing of V1 and V2 devices to take with each customer?

Phase II contractors are expected to  install and demonstrate the necessary prototype system V1 at the premises of each of the procurer. Alternatively, the developer will provide access to a lab environment in order to test the prototype by at least 10 users of each of the procurers. The protocol of testing V1 is expected to be delivered at the end of month 3 of Phase II, whereas the protocol of testing V2 is expected to be delivered at the end of month 8 of Phase II.